Hello All,
I ran into a tombstone situation the other day and wanted to have some of my Jr. Sys Admins get hands-on experience in repairing this situation. I was trying to figure out a way to create a test environment with two DCs and force one of them to tombstone so they would have to fix it (without waiting 180 days).
One of the things I did already try is go change the tombstone life attribute in the schema to 1, and power off the other DC for a week and it didn't get tombstoned.
I know this is unconventional to TRY to break something, but I want them to have hands on experience in the case of something like this happening again in production.
Any advice would be greatly appreciated, thanks!!